STENCIL SPRAY ON DRY METHOD

An ideal solution for your old floor especially when height restrictions apply. The method of application which makes the technique Stencil a must. With this unique technique, we can manufacture colored flooring onto existing surface, with a total thickness of 7-9 mm! Also, with this method we can proceed to repair old and damaged floors, saving all decommissioning costs of the damaged floor.

  • Without cost of dismantling the old floor (dismantling, labor, disposal of rubble)
  • Very fast application
  • With a total thickness of less than 1cm.
  • Durable and elegant
  • Extremely slip-resistant
  • Very economical
  • Repairable
  • In colors & patterns of your choice

BEFORE THE APPLICATION

AFTER THE APPLICATION

STEP 1

Inspection of the floor area, removal of all loose and detached parts.

STEP 2

The floor is washed with a hydrochloric acid solution under pressure, to remove organic residues.

STEP 3

If necessary and in the presence of  any chemical corrosion of the worn surface, the floor is treated with special repairing solutions. Every mechanical damage (holes and cracks) is mended with resinous sealing cement mortars.

STEP 4

Stencil resinous quartz forged cement of 3 mm height is applied. On top of it, a dense, firm, fiberglass mesh  and a second layer of the Stencil resinous quartz forged cement mortar are applied, so as to box the mesh. A proper sub-base has been formed with the focus on improving both strength and aesthetics of the new floor.

STEP 5

The floor is allowed to dry completely, then the Stencil decorative floor is constructed with the Spray on Dry technique. The special Stencil waterproof  paper with the desired pattern is placed on top.

STEP 6

The Stencil color hardener is sprayed in liquid form. The total amount of material used is 4 kg/sq.m. in a thickness of approximately 3mm.

STEP 7

Finally, the Stencil paper is removed and the new floor is embossed. A few days later, the floor is cleaned and a special impregnating sealer varnish is applied and the new floor is ready to use.